0 of 25 questions completed
Questions:
You must fill out this field. |
|
You must fill out this field. |
|
You must fill out this field. |
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
0 of 25 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Average score |
|
Your score |
|
Which are the possible outputs when you are in a control schedule process?
You might need a Resource calendars when you do the following?
You are working as a scheduler for a project to build new a sports park. The project manager asks you for the information of working days and shifts that are available for project activities. In which document will you be able to find this information?
What technique will you use to divide and subdivide work packages into activities?
In which document that you can find a hierarchical representation of resource by types that may include the skill level, grade level, or other information as appropriate to the project?
You are in the process of estimating the resources required for your project activities. What are the possible input for your current process?
You are in a 5 months project and are currently at the end of month 3. Your project teams have completed 40 % of the works and spent $25,000 from a total budget of $120,000. Your project team was supposed to have completed 60 % of works by the end of month 3. This project is:
Your project EV is $ 56,000, AC is $ 68,000, and PV is $ 75,000. The total budget of this project is $ 90,000. How much more are required to complete the project?
You are working as a project scheduler on a construction project to build a new apartment. You are currently in the process of developing the project schedule. After discussing with the project team, turns out you can schedule the landscaping work, which was scheduled to start after the finishing work of the parking space complete, to start 3 weeks prior. What kind of relations will you use for these activities in the schedule?
Your project manager determines that the underpass construction project cannot start their digging activity before the safety concerns and requirements have already been met. What kind of dependencies is this?
You have been working with your project team on identifying and sequencing activities, estimating the resources required, estimating the durations required, and now you are trying to develop the schedule. Which list might be the outputs of your current process?
A project management plan is a collection of a subsidiary plan that integrates into a comprehensive project management plan. A project management plan will define how the project is executed, monitored and controlled, and closed. Which of the following is considered part of a project management plan?
You are working in a multi year’s project. After meeting with the project team, it is clear that you can only create a detailed schedule for the first year only. A more detail schedule for the next year can only be develop after you and your team have more information and you will only get that information after you have completed half of year scheduled work for the first year. What kind of technique that you use?
You are currently in the process of figuring out the resources required to complete a critical activity. You already have an estimate that was based on the similar activity from past project but you still not convince that you have an accurate estimate; especially the condition of current project with past project is quite different. What should you do next?
Every project should have at least how many milestones?
You have been asked to calculate the to-complete performance index required to complete the project based on the new estimate at completion. Which formula will you use?
You are currently in a project where the SPI is 0.85 and the CPI is 0.9. Which one is the incorrect statement about this project?
You have just calculated that your project TCPI is 1.2. What does this mean?
Your project team has completed 50% of works for a construction project with a total budget of $ 1,250,000. So far the project has already spent $ 400,000 and is expected to perform with the current rate until the end of the project. What is the correct statement about this project?
Your project team has completed 30% of works for a construction project with a total budget of $ 1,250,000. So far the project has already spent $ 600,000 and is expected to perform with the current rate until the end of the project. What is the estimated VAC of this project?
Your project team has completed 60% of works for a construction project with a total budget of $ 1,250,000. So far the project has already spent $ 800,000 and is expected to perform with the current rate until the end of the project. What is the current cost variance of this project?
For some reasons your most senior engineer has not being on her top performance. Your project only completed 30% of scheduled works when it was supposed to complete 60% of scheduled works. Your total project budget is $ 500,000. What is the correct statement about this project?
Your project sponsor asks for total project cost estimation at completion. Currently your project suffers some minor setback and is behind schedule but things have turned around and you assume that from now on your project will perform at the budgeted rate. What formula would you use to calculate the estimation?
You are currently in the process of identifying and documenting relationships among the project activities. What will likely be the key output of this process?
Resource calendar is one of the inputs on Develop Schedule process. Which statement about Resource calendar below is incorrect?
Purpose
The process of finalizing all activities across all of the Project Management Process Groups to formally complete the project or phase.
Benefit
This process archived the project or phase information, the planned work is completed, and organizational team resources are released to pursue new endeavors.
When
This process is performed once or at predefined points in the project.
Purpose
The process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and project management plan; and communicating their disposition.
Benefit
This process allows for documented changes within the project to be considered in an integrated manner while addressing overall project risk, which often arises from changes made without consideration of the overall project objectives or plans.
When
This process is performed throughout the project.
Purpose
The process of tracking, reviewing, and reporting the progress to meet the performance objectives defined in the project management plan.
Benefit
This process allows stakeholders to understand the current state of the project, to recognize the actions taken to address any performance issue, and to have visibility into the future project status with cost and schedule forecast.
When
This process is performed throughout the project.
Purpose
The process of using existing knowledge and creating new knowledge to achieve the project’s objectives and contribute to organizational learning.
Benefit
Prior organizational knowledge is leveraged to produce or improve the project outcomes, and knowledge created by the project is available to support organizational operations and future projects or phases.
When
This process is performed throughout the project.
Purpose
The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project’s objectives
Benefit
This process provides overall management of the project work and deliverables, thus improving the probability of project success.
When
This process is performed throughout the project.
Purpose
The process of consolidating all subsidiaries plan and baselines and integrating them into a comprehensive project management plan.
Benefit
This process produces a comprehensive document that defines the basis of all project work and how the work will be performed.
When
This process is performed once or at predefines points in the project.
Purpose
The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Benefit
This process provides a direct link between the project and the strategic objectives of the organization, creates a formal report of the project, and shows the organizational commitment to the project.
When
This process is performed once or at predefines points in the project.
Purpose
The process of monitoring the status of the project and product scope and managing changes to scope baseline.
Benefit
This process maintains scope baseline throughout the project.
When
This process is performed throughout the project.
Purpose
The process of formalizing acceptance of the completed project deliverables.
Benefit
This process brings objectivity to the acceptance process and increases the probability of final product, service, or result acceptance by validating each deliverable.
When
This process is performed periodically throughout the project as needed.
Purpose
The process of subdividing project deliverables and project work into smaller, more manageable components (work package).
Benefit
This process provides a framework of what has to be delivered.
When
This process is performed once or at predefined points in the project.
Purpose
The process of developing a detailed description of the project and product.
Benefit
This process describes the product, service, or result boundaries and acceptance criteria.
When
This process is performed once or at predefined points in the project.
Purpose
The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.
Benefit
This process provides the basis for defining the product scope and project scope.
When
This process is performed once or at predefined points in the project.
Purpose
The process of creating a document that documents how the project scope will be defined, validated, and controlled. Provide guidance and direction on how scope will be managed throughout the project.
Benefit
The process of creating a document that documents how the project scope will be defined, validated, and controlled. Provide guidance and direction on how scope will be managed throughout the project.
When
This process is performed once or at predefined points in the project.
Purpose
The process of monitoring the progress status of the project and managing changes to the schedule baseline.
Benefit
This process is maintaining the schedule baseline throughout the project.
When
This process is performed throughout the project.
Purpose
The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution and monitoring and controlling.
Benefit
This process generates a schedule model with planned dates for completing project activities.
When
This process is performed throughout the project.
Purpose
The process of estimating the time or duration required to complete each project activities.
Benefit
This process provides the amount of time each activity will take to complete.
When
This process is performed throughout the project.
Purpose
The process of determining the logical relationship between each project activities.
Benefit
This process defines the logical sequence of work to obtain the greatest efficiency given all project constraints.
When
This process is performed throughout the project.
Purpose
The process of identifying activities that are required to produce project deliverables.
Benefit
This process decomposes work packages into schedule activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work.
When
This process is performed throughout the project.
Purpose
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule
Benefit
This process provides guidance and direction on how the project schedule will be managed throughout the project.
When
This process is performed once or at predefined points in the project.
Purpose
The process to monitor how the funds are being used and to manage changes to the cost baseline
Benefit
This process is maintaining the cost baseline throughout the project.
When
This process is performed throughout the project.
Purpose
The process to aggregate activity cost estimates to determine how much fund is required.
Benefit
This process determines the cost baseline against which project performance can be monitored and controlled.
When
This process is performed once or at predefined points in the project.
Purpose
The process to develop an approximate estimation of how much it will cost to complete project activities
Benefit
This process determines the monetary resources required for the project.
When
This process is performed periodically throughout the project as needed.
Purpose
The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.
Benefit
This process provides guidance and direction on how the project costs will be managed throughout the project.
When
This process is performed once or at predefined points in the project.
Purpose
The process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes.
Benefit
This process verifying that project deliverables and work meet the requirements specified by key stakeholders for final acceptance.
When
This process is performed throughout the project.
Purpose
The process of auditing the quality requirements and the results from quality control measurements to ensure that appropriate quality standards and operational definitions are used.
Benefit
This process increases the probability of meeting the quality objectives as well as identifying ineffective processes and causes of poor quality.
When
This process is performed throughout the project.
Purpose
The process of identifying quality requirements and/or standards for the project and its deliverables.
Benefit
This process provides guidance and direction on how quality will be managed and verified throughout the project.
When
This process is performed once or at predefined points in the project.
Purpose
The process of ensuring that the physical resources assigned and allocated to the project are available as planned, monitoring planned versus actual, and making corrective actions as necessary.
Benefit
Ensures that the assigned resources are available to the project at the right time and in the right place and are released when no longer needed.
When
This process is performed throughout the project.
Purpose
The process of tracking team member performance, providing feedback, resolving issues, and managing team changes to optimize project performance.
Benefit
This process influences team behavior, manage conflict and resolve issues.
When
This process is performed throughout the project.
Purpose
The process of improving competencies, team member interaction, and overall team environment to enhance project performance.
Benefit
Will results in improve teamwork, enhanced interpersonal skills and competencies, motivated employees, reduced attrition, and improved overall project performance.
When
This process is performed throughout the project.
Purpose
The process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.
Benefit
This process outlines and guides the selection of resources and assigns them to their respective activities.
When
This process is performed periodically throughout the project as needed.
Purpose
The process of estimating team resources and the type and quantities of materials, equipment, and supplies necessary to perform project work.
Benefit
This process identifies the type, quantity, and characteristics of resources required to complete the project.
When
This process is performed periodically throughout the project as needed.
Purpose
The process of estimating team resources and the type and quantities of materials, equipment, and supplies necessary to perform project work.
Benefit
This process establishes the approach and the level of management effort needed for managing project resources based on the type of complexity of the project.
When
This process is performed once or at predefined points in the project.
Purpose
The process of monitoring and controlling the project communications to ensure the information needs of project stakeholders are being met.
Benefit
Optimal information flow as defined in the communications management plan and the stakeholder engagement plan.
When
This process is performed throughout the project.
Purpose
The process of gathering and retrieving, distributing, storing, and ultimately disposing of the project information.
Benefit
Enables an efficient and effective information flow between the project team and the stakeholders.
When
This process is performed throughout the project.
Purpose
The process to define how the project information will be retrieved, maintain, distribute, store, and dispose of. This process also looks at how to maximize the efficiency and effectiveness of the communication in the project.
Benefit
Enables a documented approach to effectively and efficiently engage stakeholders by presenting relevant information in a timely manner
When
This process is performed throughout the project.
Purpose
The process of monitoring the implementation of risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project.
Benefit
This process enables project decisions to be based on current information about overall project risk exposure and individual project risks.
When
This process is performed throughout the project as needed.
Purpose
The process of implementing risk response plans.
Benefit
This process ensures that agreed-upon risk responses are executed as planned in order to address overall project risk exposure, minimize project threats, and maximize project opportunities.
When
This process is performed throughout the project.
Purpose
The process of developing options, selecting strategies, and agree on actions to address overall project risk exposure, as well as to treat individual project risks.
Benefit
This process identifies appropriate ways to address overall project risk and individual project risks.
When
This process is performed throughout the project.
Purpose
The process of numerically analyzing the effect of identified risks and other sources of uncertainty on overall project objectives.
Benefit
This process quantifies overall project risk exposure, and it can also provide additional quantitative risk information to support risk response planning.
When
This process is not required for every project, but where it is used, it is performed throughout the project.
Purpose
The process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics.
Benefit
This process helps to focus efforts on high-priority risks.
When
This process is performed throughout the project.
Purpose
The process of identifying individual project risks as well as sources of overall project risk and documenting their characteristics.
Benefit
Documentation of existing individual project risks and the source of overall project risk.
When
This process is performed throughout the project.
Purpose
The process of defining how to conduct risk management activities for a project.
Benefit
Ensures that the degree, type, and visibility of risk management are proportionate to both risk and the importance of the project to the organization and other stakeholders.
When
This process is performed once or at predefined points in the project.
Purpose
The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers.
Benefit
This process helps to determine whether to acquire goods and services from outside of the project and, if so, what – when – and how to acquire it.
When
Performed once or at predefined points in the project.
Purpose
The process of obtaining seller responses, selecting a seller and awarding a contract.
Benefit
This process helps selects a qualified seller and implement the legal agreement for delivery.
When
Periodically throughout the project, as needed.
Purpose
The process of managing procurement relationships, monitoring contract performance, and making changes and corrections to contracts as appropriate.
Benefit
Ensures that both the seller’s and buyer’s performance meet the project’s requirements according to the term of the legal agreement.
When
Throughout the project, as needed.
Purpose
The process of identifying stakeholders in your project. It is essential to identify all stakeholders on the project regularly.
Benefit
Enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders.
When
Periodically throughout the project, as needed.
Purpose
The process of developing approaches to involve stakeholders based on their needs, expectations, interests, and potential impact on the project.
Benefit
Provides an actionable plan to interact effectively with stakeholders.
When
Periodically throughout the project, as needed.
Purpose
The process of communicating with stakeholders and making sure that their expectations are being met, address any issues, and keeping the stakeholders support and interest to the project remains within the plan.
Benefit
Allows the project manager to increase support and minimize resistance from stakeholders.
When
Throughout the project.
Purpose
The process of monitoring the stakeholder relationship, communications, and engagement level and make changes to the engagement strategies and plans if required.
Benefit
It maintains or increases the efficiency and effectiveness of stakeholder engagement activities and the project evolves and its environment changes.
When
Throughout the project.